Masonry Labor Production Calculator
Estimate days and labour cost to lay brick, block or stone veneer from production rate and crew size.
Estimate days and labour cost to lay brick, block or stone veneer from production rate and crew size.
Results
Enter your details and click Calculate to see your results.
About This Calculator
Days = quantity ÷ (rate × masons). Typical rates: 400–600 bricks, 120–160 blocks or 30–40 ft² of stone veneer per mason a day. Tenders add about 60% to labour hours.
Example
Example: 5,000 bricks with 2 masons → Duration: 5.0 days for 2 mason(s).
Assumptions
Estimating aid; use your local prices and production rates.
Frequently Asked Questions
How many bricks can a mason lay a day?
About 500 on straight walls.
How many blocks a day?
Roughly 120–160.