PERT Calculator (Three-Point Estimate & Project Probability)
Calculate PERT three-point estimates from optimistic, most likely and pessimistic durations for each task. Gives the expected project time, standard deviation, P50/P80/P95 durations and the…
Calculate PERT three-point estimates from optimistic, most likely and pessimistic durations for each task. Gives the expected project time, standard deviation, P50/P80/P95 durations and the probability of finishing by a deadline.
Results
About This Calculator
For each task, PERT expected time E = (O + 4M + P) ÷ 6 and standard deviation σ = (P − O) ÷ 6. For tasks done one after another (the critical path), add the E values and combine the σ values as √(σ₁² + σ₂² + …).
Commit to P80 or P95 rather than the expected value, which you'll miss about half the time.
Example
Example: three tasks estimated at 2/4/8, 3/5/10 and 1/2/4 days give an expected 12 days ± 1.62. You can promise 13.4 days with 80% confidence; 89.2% chance of finishing within 14.
Assumptions
Tasks are sequential and independent, and the total is roughly normally distributed. For parallel tasks, list only the critical path.
Frequently Asked Questions
What is the PERT formula?
E = (Optimistic + 4 × Most likely + Pessimistic) ÷ 6.
What is P80 in project estimates?
The duration you'll meet 80% of the time: expected + 0.84 standard deviations.