PERT Calculator (Three-Point Estimate & Project Probability)

Calculate PERT three-point estimates from optimistic, most likely and pessimistic durations for each task. Gives the expected project time, standard deviation, P50/P80/P95 durations and the…

Results

Enter your details and click Calculate to see your results.
About This Calculator

For each task, PERT expected time E = (O + 4M + P) ÷ 6 and standard deviation σ = (P − O) ÷ 6. For tasks done one after another (the critical path), add the E values and combine the σ values as √(σ₁² + σ₂² + …).

Commit to P80 or P95 rather than the expected value, which you'll miss about half the time.

Example

Example: three tasks estimated at 2/4/8, 3/5/10 and 1/2/4 days give an expected 12 days ± 1.62. You can promise 13.4 days with 80% confidence; 89.2% chance of finishing within 14.

Assumptions

Tasks are sequential and independent, and the total is roughly normally distributed. For parallel tasks, list only the critical path.

Frequently Asked Questions

What is the PERT formula?

E = (Optimistic + 4 × Most likely + Pessimistic) ÷ 6.

What is P80 in project estimates?

The duration you'll meet 80% of the time: expected + 0.84 standard deviations.

Related Calculators

About the Author

Imran Hossain
Imran Hossain

Professional SEO, Digital Marketer Specialist

I am a Certified Google Ads Expert And Professional SEO, Digital Marketing Specialist

View full profile