EMV Calculator

Calculate expected monetary value (EMV) for project risk analysis or a decision tree — probability × impact across up to five risks and opportunities.

Results

Enter your details and click Calculate to see your results.
About This Calculator

List each risk with its probability and cost as a negative number, and each opportunity with a positive gain. The total EMV is the contingency reserve the risks justify (if negative) or the expected upside.

For a decision-tree branch, enter every possible outcome of that branch so the probabilities add to 100%.

Example

Example: a 20% chance of a $50,000 delay, 10% chance of a $120,000 supplier failure and 30% chance of a $40,000 saving give an EMV of −$10,000 + −$12,000 + $12,000 = −$10,000 — a $10,000 contingency reserve.

Assumptions

EMV = Σ probability × impact (PMBOK quantitative risk analysis). Assumes you're risk-neutral; real decisions may weigh large losses more heavily — see the Expected Utility Calculator.

Frequently Asked Questions

Why are risks entered as negative numbers?

So threats and opportunities can be added together: threats reduce value, opportunities increase it.

Do the probabilities need to add up to 100%?

For independent project risks, no. For a decision-tree branch, the outcomes should cover every possibility and total 100%.

Related Calculators

About the Author

Imran Hossain
Imran Hossain

Professional SEO, Digital Marketer Specialist

I am a Certified Google Ads Expert And Professional SEO, Digital Marketing Specialist

View full profile