EVM Calculator

Calculate earned value management (EVM) metrics for a project — planned value, earned value, cost and schedule variance, CPI, SPI, EAC, ETC, VAC and TCPI.

Results

Enter your details and click Calculate to see your results.
About This Calculator

Enter the total budget, how much of the work should be done by now according to the plan, how much actually is, and what you've spent. CPI and SPI below 1 mean over budget and behind schedule.

Example

Example: a $500,000 project that should be 50% done is 40% done after spending $220,000. EV = $200,000, so CPI = 0.91 and SPI = 0.80. At this efficiency it will cost $550,000 — $50,000 over budget.

Assumptions

EAC = BAC ÷ CPI (assumes current cost performance continues); TCPI = (BAC − EV) ÷ (BAC − AC), the efficiency needed on the remaining work to finish on budget. PMI's PMBOK standard formulas.

Frequently Asked Questions

What does a CPI of 0.9 mean?

You're getting 90 cents of planned work for every dollar spent — about 11% over budget.

What is a good SPI?

1.0 is on schedule; above 1 is ahead. Below about 0.9 usually needs corrective action.

Related Calculators

About the Author

Imran Hossain
Imran Hossain

Professional SEO, Digital Marketer Specialist

I am a Certified Google Ads Expert And Professional SEO, Digital Marketing Specialist

View full profile