Construction Activity Duration Calculator

Estimate how long a construction activity will take from quantity, crew production rate, number of crews and weather allowance.

Results

Enter your details and click Calculate to see your results.
About This Calculator

Days = quantity ÷ (rate × crews × efficiency) ÷ (1 − weather allowance).

Example

Example: 12,000 ft² of drywall at 800 per crew-day → Duration: 10 working days.

Assumptions

Estimating aid; use your local prices and production rates.

Frequently Asked Questions

How do I estimate activity duration?

Quantity ÷ realistic production per crew-day.

Do more crews always help?

Until they get in each other's way.