Construction Activity Duration Calculator
Estimate how long a construction activity will take from quantity, crew production rate, number of crews and weather allowance.
Estimate how long a construction activity will take from quantity, crew production rate, number of crews and weather allowance.
Results
Enter your details and click Calculate to see your results.
About This Calculator
Days = quantity ÷ (rate × crews × efficiency) ÷ (1 − weather allowance).
Example
Example: 12,000 ft² of drywall at 800 per crew-day → Duration: 10 working days.
Assumptions
Estimating aid; use your local prices and production rates.
Frequently Asked Questions
How do I estimate activity duration?
Quantity ÷ realistic production per crew-day.
Do more crews always help?
Until they get in each other's way.